Cowley Substation Phase 1,2 & 3

Project Summary

MCE was contracted by our client Britannia Construction LTD to deliver the groundwork and reinforced concrete package as part of the construction of the worlds largest hybrid system as an extension to the existing substation at Blackberry Lane, Cowley, the works where split into 3 phases. 

Phase 1 being the construction of a cable incomer enclosure to accommodate the incoming cables and switch house. 

Phase 2 was the construction of series or RC slabs and plinths to accommodate the lithium ion stack containers and transformers 

Phase 3 was the installation of a series of reinforced concrete capping and ground beam to support the installation of the infinity energy storage units.  